Serial No. |
Date |
Project name |
Control system |
Remarks |
1 |
2002 |
Tianjin Dagang Power Plant Oil-burning boiler technology reconstruction engineering Phase I(2×328.5MW )DCS SYSTEM |
INFI-90 |
|
2 |
2003 |
Fushun Petrochemical Company Detergent Chemical Factory Dynamic Branch Factory(4 boilers 2 machines)DCS SYSTEM |
ABB AC800F |
|
3 |
2003 |
Wenzhou Power Plantflue gas desulfurization(2×300MW )DCS SYSTEM |
INFI-90 |
|
4 |
2003 |
Guohua Beijing Thermal Power Plant, Jianfeng Thermal Network Control system |
ABB AC800F |
|
5 |
2004 |
Shajiao C Power Plant flue gas desulfurization(3×600MW )DCS SYSTEM |
INFI-90 |
|
6 |
2005 |
Xingtai Guotai Power Plant(2×300MW)set DCS SYSTEM |
TOSMAP-DS |
|
7 |
2005 |
Iran Tawazi Power Station(2X55MW) Set DCS SYSTEM |
ABB AC800F |
|
8 |
2005 |
Zhuhai Power Plant(2×600MW)flue gas desulfurization DCS system |
TOSMAP-DS |
|
9 |
2005 |
Wangqu Power Plant(2×600MW)flue gas desulfurization DCS system |
ECS-100 |
|
10 |
2005 |
Diandong Power Plant(4×600MW) flue gas desulfurization DCS system |
SYMPHONY |
|
11 |
2005 |
Fangchenggang Power Plant(2×600MW)Supercritical Set DCS system |
SYMPHONY |
|
12 |
2005 |
Huarun Gucheng Power Plant (2X300MW)flue gas desulfurization DCS system |
ECS-100 |
|